WEEK |
MONDAY |
TUESDAY |
WEDNESDAY |
THURSDAY |
FRIDAY |
|
Sept 5-9 |
Labour Day |
Introduce Cardboard Boat Project Orthographic Drawing pg 94 Bar Holder |
Working on Boat sketches |
Working on Boat sketches Internet research due Ortho Dwg Due |
|
|
Sept 12-16 |
Working on mock-ups and testing them for stability and max weight held |
Working on mock-ups and testing them for stability and max weight held Orthographic drawing due |
Working on mock-ups and testing them for stability and max weight held |
Working on mock-ups and testing them for stability and max weight held Working on Acad Drawing along with cut-out pattern |
Working on Acad Drawing along with cut-out pattern Mock-ups, sketches, and calculations due |
|
Sept 19-23 |
Working on Acad Drawing along with cut-out pattern |
Start manufacturing the real thing out of cardboard with a partner Personal Orthographic drawing due |
Manufacturing real cardboard boat |
Manufacturing real cardboard boat |
Manufacturing real cardboard boat Early release day |
|
Sept 26-30 |
Manufacturing real cardboard boat |
Manufacturing real cardboard boat (don't forget decorations) Modify drawing so it is as built and submit for marking with boat |
Grade 12 Retreat Manufacturing real cardboard boat |
Grade 12 Retreat Manufacturing real cardboard boat |
Grade 12 Retreat Finished Boat must be in shop with drawing and decorations for evaluation |
|
Oct 3-7 |
Float them or sink them at Brock pool (cardboard boats) all afternoon |
Working on project report for cardboard boats
|
Cardboard Boat Project Report Due
|
Mcmaster Engneering Olympics |
P.A. Day |
|
Oct 10-14 |
Thanksgiving Day |
Introduce Robotics Project |
Working on internet research |
Working on design sketches |
Working on design sketches Internet research due for Robotics |
| Oct 17-21 | Start Manufacturing Robot Mock-ups Safety Tours |
Safety Tours Manufacturing Mock-ups Review use of Vernier
|
Manufacturing Mock-ups Safety Tours |
Manufacturing Mock-ups Safety Tours |
Mock-ups and sketches due for evaluation |
|
Oct 24-28 |
Big Meeting in groups to decide on preliminary design |
Making Full scale mock-up of robot Begin Drawing robot on Acad and/or Inventor |
Making Full scale mock-up of robot Drawing robot on Acad and/or Inventor |
Making Full scale mock-up of robot Drawing robot on Acad and/or Inventor |
Making Full scale mock-up of robot Sketching full robot |
|
Oct 31-Nov 4 |
Robot Mock-up Due along with full sketch and explanation of design |
Starting to Manufacture frame and drive system |
Manufacture frame and drive system |
Manufacture frame and drive system |
Manufacture frame and drive system |
|
Nov 7-11 |
Manufacture frame and drive system |
Manufacture frame and drive system |
Manufacture frame and drive system |
Manufacture frame and drive system |
Manufacture frame and drive system |
|
Nov 14-18 |
Manufacture frame and drive system |
Manufacture frame and drive system |
Manufacture frame and drive system |
Manufacture frame and drive system |
Frame and drive system completed for evaluation with acad or inventor dwg |
|
Nov 21-25 |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
|
Nov 28-Dec 2 |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
|
Dec 5-9 |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
Manufacture Block pick-up and delivery system |
|
Dec 12-16 |
Manufacture Ball pick-up system |
Manufacture Ball pick-up system |
Manufacture Ball pick-up system |
Manufacture Ball pick-up system |
Manufacture Ball pick-up system |
|
Dec 19-23 |
Finish Robot |
Finish Robot |
Finish Robot |
Finish Robot |
Christmas Vacation |
|
Jan 9-13 |
Finish Robot |
Finish Robot |
Finish Robot |
Finish Robot |
Finish Robot |
|
Jan 16-20 |
Robot must be finished for Open House Tonight |
Robot Finished along with full drawings |
Robot Finished along with full drawings |
Robot Finished along with full drawings |
Robot Finished along with full drawings must be handed in today |
|
Jan 23-27 |
|
|
|
|
|